QEW Improvements from East of Cawthra Road to
West of Etobicoke Creek
Ministry of Transportation Contract #2021-2127
This section of the website will have updates for major closures. Nighttime lane closures can be expected throughout construction.
For more details on traffic impacts from this contract and others across the province please visit https://511on.ca/
Current Closures
Project Milestones
Full Closure of QEW in both directions for Dixie Bridge Demolition and Storm Sewer Installation
Saturday, March 22, 2025 8:00 pm - 11:00 am - QEW Westbound (WB) Full closure
Saturday, March 22, 2025 8:00 pm - 8:00 am - QEW Eastbound (EB) Full closure
Sunday, March 23, 2025 8:00 am - 11:00 am - QEW Eastbound (EB) Two-lane closureFull Closure of QEW in both directions for Dixie Bridge Demolition and Storm Sewer Installation
Saturday, March 8, 2025 8:00 pm - 11:00 am - Full Closure
Saturday, March 15, 2025 8:00 pm - 6:00 am - Full Closure followed by two-lane closure until 12:00 pm
Completion of Ogden Pedestrian Bridge - December 23, 2024
Brentano Blvd from Feldwood Road to the West - Sanitary Sewer Replacements (Approx. 6 weeks)
Late Summer 2024: New Dixie Bridge - Opened September 2024
Fall 2024: Haig Boulevard Sewers Complete
December 2024: Eastbound lanes of North Service Road between Stanfield Road to the new Dixie Road
- Opened December 19, 2024Spring 2025 - Demolition of existing Dixie Road Underpass Bridge